Utility Infrastructure Improvement Project

Building a Better Bal Harbour for You

Project Overview and Benefits

The Village is currently constructing and repairing sections of the underground utilities within the gated residential community and Collins Avenue. The work being performed will enhance the performance and longevity of the water, sanitary sewer and stormwater systems that run underground and connect to the homes. Paving operations will follow the underground work to restore roadways throughout the area. When complete, these improvements will provide our residents and guests with a safe and efficient water supply system, a sanitary sewer system that meets regulatory requirements while ensuring the system reduces groundwater infiltration and an enhanced stormwater system to more efficiently disperse stormwater after rain events and minimize any pollutants from stormwater discharging into Biscayne Bay.

While design work for these phases began many years ago, construction started in Phases 3 and 4 in April of 2020, and in Phases 5 and 6 in 2022. We anticipate all phases of work to be completed in 2027. Below is a brief synopsis of the work and schedule within each zone.

Project Status as of March 27, 2024

The overall neighborhood’s improvements have been broken into zones. This helps focus the contractor’s area of impact and fully completes larger sections of the neighborhood at a time. This also allows us to minimize traffic and utility service disruptions throughout the neighborhood.

MAJOR WORK – Water Main Installation and Water Meter Relocations Along Park Drive Begin in April

Beginning the first week in April, a new water main will be installed along the east side of Park Drive between Bal Cross Drive and Harbor Way East. Domestic and irrigation water meters in this area will also be relocated to the front of properties. The apartment buildings on east side of Park Drive facing Collins Avenue will also have new water services installed at the rear of the property wall. Future work also includes the construction of new curb and gutter and repaving the roadway. See below Project 5A for additional details.

Map of Phased Areas

Project Phases

Phase 1b – Completed

Phase 2b – Completed

Phase 3a & 3b (completed)

Phase 4 – Completed

Phase 3c (under construction)

Pending Work Includes:

  • Placing new asphalt along the roadway.

Anticipated Schedule:

  • Expected completion in this area in 2025.

Phase 5a (under construction)

Pending Work Includes:

  • Water Main Installation and Water Meter Relocations Along Park Drive
  • Replacing and installing water mains; relocating water services from rear of homes to front of homes
  • Adjusting or replacing stormwater inlets and grates
  • Replacing damaged curb and gutter
  • Placing new asphalt on the roadway

View flyer for additional details.

Anticipated Work Schedule:

  • First week of April through December 6, 2024*
  • Daily, 8:30 a.m. to 5:30 p.m.
  • Property owners will be notified days in advanced by the contractor and/or Village staff when workers are required to work at the rear of property or easement area.
  • Use caution when driving or walking near the work zone. Follow posted signs.

*Please note that this schedule could change due to bad weather or other unexpected conditions.

Phase 6a & 6b (under construction)

Pending Work Includes:

  • Replacing and installing water mains; relocating water services from rear of homes to front of homes
  • Major stormwater drainage improvements
  • Removal and replacement of damaged curb and gutter
  • Placing new asphalt along the roadway

Anticipated Schedule:

  • Stormwater drainage improvement work expected to start by end of 2024.
  • Expected completion in this zone by end of 2025

Phase 7 (in design)

Pending Work:

  • Performing stormwater drainage improvements near Bal Bay Drive and Bal Cross Drive (in conjunction with 5b and 5c).
  • Repairing the stormwater pump station adjacent to Harbour Way West.

Anticipated Schedule:

  • Early 2024 through 2025

Phase 5b & 5c (under construction)

Pending Work Includes:

  • Stormwater drainage improvements in conjunction with Phase 7
  • Removal and replacement of damaged curb and gutter
  • Placing new asphalt along the roadway

Anticipated Schedule:

  • Expected completion in this zone by summer of 2025 in coordination with the work in Phase 7.

What You Should Expect

  • Routine project updates will be distributed to provide information on upcoming work and anticipated traffic impacts.
  • Future paving operations will require coordination with each of the homes in that area as vehicle traffic will be limited throughout the work zones during the placement of asphalt. More information will come before the paving is scheduled.

Text & Email Updates

Text Notifications
Sign up to receive text message updates regarding this project by texting “BetterBH24” to “69310.”

Email Notifications
Sign up to receive regular email updates regarding the Utility Infrastructure Improvement Project and applicable road closures.

Who to Contact

For more information, please contact Public Information Officer Heather M. Leslie via email at [email protected] or by phone at 305.905.5876. You can also contact Village Hall at 305.866.4633.