Utility Infrastructure Improvement Project

Status as of September 5, 2025

Building a Better Bal Harbour for You

Project Overview and Benefits

The Village is currently improving the underground utilities within the gated residential community. Street paving follows the underground work to restore roadways throughout the area. While design work for these phases began many years ago, Phase 3 and 4 constructions 305-993-7361arted in April of 2020, and in Phases 5 and 6 in 2022. We anticipate all phases of work to be completed by 2027.  

While design work for these phases began many years ago, construction started in Phases 3 and 4 in April of 2020, and in Phases 5 and 6 in 2022. We anticipate all phases of work to be completed in 2027. Below is a brief synopsis of the work and schedule within each zone.

Once completed, these improvements will provide our residents and guests with:

  • A safe and efficient water supply system
  • A sanitary sewer system that meets regulatory requirements
  • A system that reduces groundwater infiltration
  • An enhanced stormwater system that more efficiently disperses stormwater after rain events
  • A system that minimizes any pollutants from stormwater discharging into Biscayne Bay.

Below is a brief synopsis of the work and schedule within each zone.

The overall neighborhood improvements have been broken into zones or phases. This helps focus on the contractor’s area of impact and completes larger sections of the neighborhood in a strategic way to minimize traffic and utility service disruptions throughout the neighborhood.

Completed Projects:
Phase 1B
Phase 2B
Phase 3A & 3B
Phase 4
Phase 5A

Under Construction and Future Work
Includes milling and paving along the roadway. Removal and replacement of damaged curb and gutter. Replacing the installing water mains, relocating water services from rear of homes to front of homes, and the repair and reconstruction of the Stormwater Pump Station on Harbour Way West.

Phase 3C

Milling and Paving Scheduled For Early 2027

Phase 5B & 5C

Stormwater Drainage Improvements

Phase 6A

Scheduled for October 2025

Phase 6B

Scheduled for November 2025

Phase 7

Reconstruction of the Stormwater Pump Station – Scheduled for October 2025


Future Project Phase

Phase 3D
Phase 8 – Proposed Drainage Improvement Project For The Area Of 6A Along The New Stormwater Pump Station Near The Intersection Of Park Drive And Bal Cross Drive. Pending Funding

Satellite image of Bal Harbour neighborhood, with aerial view of properties, along with overlay showing areas of various phases of Utility Infrastructure Improvement Project. Phases 1b, 2b, and 4 in teal, 3a in orange, 3b in yellow, 3c in purple, 3d in dark purple, 5a in green, 5b in maroon, 5c in blue, 6a in light orange, 6b in light purple, 7 in red, and 8 in dark blue.


What You Should Expect

  • Routine project updates will be distributed to provide information on upcoming work and anticipated traffic impacts.
  • Future paving operations will require coordination with each of the homes in that area as vehicle traffic will be limited throughout the work zones during the placement of asphalt. More information will come before the paving is scheduled.

Text & Email Updates

Text Notifications
Sign up to receive text message updates regarding this project by texting “BetterBH24” to “69310.”

Email Notifications
Sign up to receive regular email updates regarding the Utility Infrastructure Improvement Project and applicable road closures.

Who to Contact
For more information, please contact Public Works or 305.993.7361.